Researchers from the Fraunhofer Institute for Systems and Innovation Research in Germany, ETH Zurich, and the Technical University of Denmark set out to estimate how much it would cost to transport hydrogen by pipeline in different regions of the world. To do this, they effectively laid out around 5,000 potential routes on a digital map between 264 regions, taking into account terrain features and the cost of project financing in different countries. It turned out that, depending on these conditions, costs can differ by almost a factor of three. The lowest cost was found in Europe – 15 euros per MWh per 1,000 km. In North America the figure was 15.6 euros, in Asia 16.2 euros, in South America 17.1 euros, and in Africa 17.2 euros.
The accuracy of such calculations will become increasingly important as hydrogen energy develops. Today, hydrogen is transported by pipeline mainly over short distances between industrial facilities, and the total length of such lines worldwide is around 5,000 km. By 2050, the length of hydrogen pipeline infrastructure could grow to 209,000 km, partly due to the development of trunk networks. About a quarter of global hydrogen demand is expected to be linked to international trade.
At the same time, building hydrogen pipelines is inherently more complex than laying ordinary gas pipelines: hydrogen can penetrate the metal structure and cause embrittlement, increasing the risk of cracking. But even when the technical requirements for the pipe itself are known, determining the cost of a specific route in advance is not straightforward.
At present, the cost of future hydrogen pipelines is often estimated quite simply: the straight-line distance between two points is taken and then usually increased by a factor of 1.2–1.4 to account for the fact that a pipeline cannot follow the shortest possible path. The resulting length is then multiplied by the average cost of building a kilometer of pipe.
However, an actual route may encounter mountains, major cities, nature reserves, or deep-sea areas along the way. In that case, its length – and, as a result, the construction cost – will be quite different. An analysis of existing international oil and gas pipelines showed that their actual routes can be up to 4.76 times longer than the straight-line distance between the starting and ending points.
To bring the calculations closer to real-world conditions, the researchers divided the Earth’s surface into approximately 12.7 million cells, each about 42.5 km² in area. For each cell they took into account terrain, land-use type, population density, protected natural areas, sea depth, and the presence of existing pipeline corridors. For example, flat and sparsely populated terrain barely increases the base construction cost, whereas steep mountain slopes can raise it fourfold. The model did not route a pipeline through areas with a population density above 4,000 people per km², or through sea areas deeper than 3,000 m. The presence of existing pipeline infrastructure, by contrast, made it possible to reduce costs. In addition, the cost of raising capital – which depends, among other things, on economic, political, and legal risks – was factored in separately for each country. As a result, the model sought not simply the shortest route between two points, but the most cost-effective one.
How local conditions change a pipeline’s route and construction costs is clearly illustrated by specific examples. A 2,909 km pipeline from Benin to Algeria turned out to be feasible to build almost in a straight line: it runs mainly through desert and savanna areas with low population density and partly follows existing infrastructure corridors. On the route between China’s Fujian province and Shanghai, the path deviates from a straight line by only 6%, yet rugged terrain, farmland, forests, sea sections, and densely populated areas more than doubled the estimated construction cost.
In the case of the route from the Indonesian island of Sumatra to Sri Lanka, for example, the main problem was the depth of the Bay of Bengal. A direct pipeline is impossible because of areas deeper than 3,000 m, so the route had to be laid around them – through shallower areas near Myanmar and Bangladesh and then through India. As a result, its estimated length reached 5,478 km – twice the straight-line distance. Given the additional construction challenges, the estimated capital costs rose by roughly a factor of 2.8 compared with a hypothetical direct route with no geographical obstacles.
Overall, for nearly half of the routes examined, real-world geography increased the estimated costs by more than 40% compared with laying the pipeline in a straight line.
The researchers also tested how much a more accurate cost estimate could affect future hydrogen trade. To do this, they used five scenarios for the development of the European energy system through 2050 and replaced the standard cost estimates with costs calculated for each specific route. As a result, transport volumes changed by more than 1% for at least 83% of the routes used. In one scenario, half of the hydrogen flows changed by more than 50%, while between Austria and the Czech Republic the direction of supply even reversed: whereas under the standard calculation Austria imported hydrogen from the Czech Republic, after accounting for geographical features and the cost of specific pipelines, it instead became an exporter.
The tool developed by the research team is already available for calculating potential routes and can be used in planning hydrogen infrastructure. Going forward, the researchers plan to further develop the model to account for the possibility of converting existing gas pipelines for hydrogen transport, as well as for the shared use of infrastructure by multiple routes.